The 1996 Kids Park Gets One More Christmas Break Before Gulf Shores Rebuilds It

November 12, 2026

Kendall Phillips was 6 years old when she painted her hand and pressed it onto the wall of the newly finished Kids Park in 1996. Her father was one of about 1,500 volunteers who built the wooden fortress at Johnnie Sims Park, and the build took six days. Thirty years later she came back with three children of her own to tell the city what the next version should look like. Gulf Coast Media reported her story from the public input event this spring.

"We were raised in this park, and now we get to raise our kids here," she told the paper.

The new Kids Park keeps the old one's footprint, shade trees and designer. The handprint wall stays, and a second one gets added. The structure Phillips's father helped build still comes down. On September 28, the City Council approved the redesign, and the city moved construction to early 2027 so families can use the existing playground through Christmas break. That gives you about seven weeks from today to climb, photograph and find your family's mark on the 1996 wood.

The city already decided once against a catalog playground

The rebuild was coming for a long time. According to the city, a 2014 study found the wooden playground nearing the end of its life. Since then, Gulf Shores has kept it safe with inspections, repairs and sealant.

The city first proposed redoing the park in 2019, and that round showed how much the wood mattered. Grant Brown, the city's director of recreation and cultural affairs, told Gulf Coast Media in June that plastic and metal systems came up as options. Mayor Pro Tempore Phillip Harris joined the community and council push to keep the wooden character. As Brown recalled it, Harris said:

"A playground like those, I will go and I will watch my kids play. A playground like we have there, that Leathers did, that kind of charming and quaintness and structure, I will actually go in there and play with my grandchildren."

That position won out. The city hired Leathers & Associates again, the same firm behind the 1996 playground. The September 2 proposal to the city says the design work assumes "standard design services based on the original design by L&A." Brown himself has a stake in the original. He and his wife, Sarah, lived nearby with their newborn daughter in 1996 and volunteered on the submarine section of the playground.

What carries over, and what gets replaced

What stays

  • The footprint and the shade. "They are going to use the original footprint, and the trees that keep the shade canopy there is really important," Brown told Gulf Coast Media.
  • The handprint wall and the engraved bricks. The city's Reimagine Kids Park page commits to "every endeavor" to preserve both.
  • A new handprint wall gets added for the kids who grow up on the new playground.

What changes

  • The material. The new structure uses mostly recycled plastic lumber, expected to last at least 30 years.
  • The ground underfoot. The surface will combine engineered wood fiber and artificial turf, which the city chose for accessibility, durability and lower maintenance.
  • Access. Brown said accessibility will be part of every section of the design, not limited to meeting ADA minimums. "We want all children to play together," he told the paper.

The Leathers proposal sizes the design at about 12,400 square feet, built to current ASTM F1487 and CPSC safety standards. Students in first through third grade also sent in drawings of their own "Reimagined Kids Park" for the designers to consider.

Why the opening moved past Christmas

Gulf Shores originally planned to have the new park open this fall. The schedule slipped by about a year, and the budget grew with it.

When What the schedule said
Spring 2026, city project page Construction in September, new Kids Park opening in November
April 29, 2026, Gulf Coast Media Construction in September, completion late November or early December
September 2, 2026, Leathers proposal Completion estimated for 2027, about 6 to 7 weeks of construction
October 5, 2026, city release Construction shifts to early 2027, existing playground open through Christmas break
Current city project timeline Construction January 2027, completion mid to late 2027

The money moved too. In late March the council approved a $940,000 project, with $39,000 of it set aside for design. According to the city's October 5 announcement, the 2026 Capital Budget carries $950,000 for the replacement. The approved safety surfacing adds $150,000, so the total project budget is $1,100,000. Most of the $160,000 increase from the spring figure comes from that surfacing decision.

The city wrote that it moved construction to early 2027 "to avoid any disruptions," so the existing playground stays open through the holidays.

Fewer hands than 1996, but still some

The original park was a classic community build, with 1,500 volunteers working over six days. The 2027 version is what the city calls a hybrid build. Leathers crews do most of the work, and city employees help. In June, Brown told Gulf Coast Media that the in-house labor is how the city plans to stretch roughly $900,000 in construction money further.

The Leathers proposal spells out the split. Leathers bills $35,900 for pre-construction design and project management and $449,247 for its construction crew. The city handles demolition of the old structure and heavy equipment, and it supplies eight skilled workers for five straight 40-hour weeks alongside the Leathers crew.

Residents still have a part in it. In April, Brown said volunteers would get to help with certain portions of the work, including the new handprint wall. "We do feel like there is some value in having some sweat equity," he told Gulf Coast Media. The city's project page says it wants to include the community during the build. Anyone who missed the survey and wants to get involved can email Grant Brown at [email protected].

What to see at Sims Park before January

The handprints and bricks are supposed to survive the rebuild, but they won't sit inside the same wooden fortress again. Over the holidays you can still see the 1996 playground as a whole, with its built-in history:

  1. Find the handprints. If you or your parents worked on the 1996 build, your family's handprint may be on that wall. The city has promised to try to preserve it, and a photo of it in its original setting is worth having either way.
  2. Look for the engraved bricks. They are the other feature the city has committed to save. Take a photo of any with a family name before the work begins.
  3. Climb the submarine. It's the section Grant Brown and his wife helped build as volunteers in 1996.
  4. Bring the kids who drew designs. If your first, second or third grader sent in a drawing, they'll get to see the playground their ideas are replacing.

Sims Park is also where Gulf Shores held its Community Christmas last December, with Santa pictures, crafts and a Snowball Drop on December 4, 2025. If the city holds it there again this year, it will be the last Community Christmas with the original playground in the background.

I follow city projects like this one because they change how Gulf Shores feels to the people who own property here, and Kids Park has been part of that for 30 years. If you're weighing a second home or rental near Sims Park, or your family has roots here and you want to talk about what's changing around town, Vince Burchfield is glad to help. Let's Connect.